Thursday, September 10, 2009

What were you doing on 09.09.09?


Well - we know there were a lot of workers up at our new facility. In this picture, a crew was working on the fencing that will enclose the outside patio area next to the cafeteria.









And in this next picture, you'll see that the walls in the showroom have started to go up. Our board room and some sales offices have also been framed out on the first floor.















Below, the pick mod is completed and the warehouse mezz is around 65% completed - flooring is going down on the 3rd floor.















Got drywall? We do - this stack is for the first floor office area. The second floor area is just about complete.















Planned for next week - beginning the drop ceiling on the second floor and completion of the offices and drywall on the first floor so keep tuned and check back often for updates.