Above, the final section of racking is being installed for the very narrow aisle storage area - approximately 50% complete. This should be completed by the end of this week. Below, the second floor offices are moving right along - ceiling grids are in and painting is in progress. HVAC ducts are being installed - note that the ends are covered with blue plastic so dust does not get into the units - part of the things we needed to do for our LEED certification. On the first floor, most of the sheet rock is now hung and work is beginning in the x-ray showroom.