Monday, November 23, 2009
The Final Weeks
Wednesday, November 11, 2009
Countdown to Moving Day: 1 Month, 4 Days

On the left is an area we haven't seen too much of yet. The restrooms, lined with decorative tile, add a nice touch to the building as a whole. On the right is a shot of the progress in the lower level offices. They're coming along and should be seeing some rapid transformation in the days and weeks to come.
Here's a look at the completed exterior.
On the left is a shot of all the work going on in the warehouse. The conveyor installation has been a tall task but is drawing to a close. On the right is the progress in the upper level offices. Carpet has been laid, paint is on the walls and some doors have even been installed.
Thanks again to Sharon for the photos!
Wednesday, October 28, 2009
Starting to Feel Like Benco
Thanks again to Sharon for her weekly photo trips to Pittston.
Tuesday, October 20, 2009
One Week Closer
Tuesday, October 13, 2009
Continued Progress......Finer Details
The Benco Headquarters project continues to move forward at a very rapid pace - multiple contracting crews continue to work on finishing up the construction "on schedule" and are getting into the "finer details" of the project. Above, you can see the tile beginning in the bathrooms which is BEAUTIFUL!Below, conveyor installation continues to move along .
Below is a catwalk that connects the warehouse mezz to the large pick module.
And over this past weekend, Bob Hunt, Keith Budurka and TIS team were in to oversee bringing in the temporary generator for the Bear Creek facility and making sure it worked - TIS handled bringing our computer systems down Saturday morning and back up successfully for Monday morning with no issues. Below is a picture of the temporary generator - this week, the existing generator will be moved up to CenterPoint and hooked up which, with the other new 500kv generator, will be able to keep us fully in business during any electrical outages.Tuesday, October 6, 2009
Rolling Along.........
Above, the final section of racking is being installed for the very narrow aisle storage area - approximately 50% complete. This should be completed by the end of this week. Below, the second floor offices are moving right along - ceiling grids are in and painting is in progress. HVAC ducts are being installed - note that the ends are covered with blue plastic so dust does not get into the units - part of the things we needed to do for our LEED certification. On the first floor, most of the sheet rock is now hung and work is beginning in the x-ray showroom.Monday, September 28, 2009
Small Steps for Big Changes
Taking a look inside, the second floor office area (top picture) is just a few coats of paint and some wiring away from cubicle layouts. In the warehouse, the mezzanine is taking shape (middle picture) and conveyor equipment (bottom picture) has finally been delivered, with installation scheduled to be getting underway very soon.
As always, thanks to Sharon for the photos and thanks for checking in! Come back soon!